Demand load factor: PE Power General Applications practice question

A plastics plant served at 480 V has a connected load of 2,000 kW. Over a 30-day billing month, its demand factor is 0.60 and its monthly load factor is 0.55. The utility tariff charges $14.50 per kW of monthly maximum demand plus $0.068 per kWh of energy.

The plant's total monthly electric bill is most nearly:

Answer choices

Try the next free question →